Gerardin Travels        

Le Premier on the left of JoLi' Folie

The "boys" were moving right along now

with the interior.

Kathy being awarded for her diagraming

artwork.

The skylight was now varnished and

installed. View looking IN to galley.

Our cabin, now had walls and carpet.

Windows were not trimmed.

Joe had installed the white ceiling and

most of the radiators.

Forward cabin windows were still

unfinshed + held open with sticks.

The salon still needed walls to mount

radiators. Ceiling complete.

Oak stairs down to salon now installed.

Guest cabin bath

Guest cabin was pretty much done.

...and always there was laundry.

July/August 2003 — Progress Report on Fit-Out

        Welcome! 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 January February May / June June / July July / Aug August September October Year End November 2002 2001 France 2001 Net Result 1999-2000 Net Result

In mid-July we moved to side tie to our friends on Le Premier on the Saône River.

If the "boys" had a few spare minutes they would be able to help us with our work onboard.

Joe installed the ceiling and radiators and finished installing the central heating system.

Lisa varnished the skylight and painted the decks.

We were now 30 days into the record-breaking heat spell that devastated Europe.

 

Click on any image to view larger images or start a slide show

 